When you apply a scheme of learning to a class, we will automatically push back the due date for any homework that would be due in a holiday week.

You can edit or add holiday dates by selecting Management on the left-hand menu and then selecting School Settings.

For example:

  • A class has homework set on Wednesday and due on Tuesday.

  • Half-term in the school is from 12th to 16th February.

  • The homework set on Wednesday 7th February is due in on Tuesday 20th rather than on the 13th during half-term.